7,938 beneficiaries benefited from the rehabilitation of the water network.
Rehabilitation of the sewage network with a length of 18,400 meters.
Rehabilitation and protection of the open well located in Wadi Khaifa to prevent the well from being destroyed and polluted in the future due to rainwater flow.
Construction of valve chambers in safe locations that cannot be affected by water tables, transportation or garbage collection sites.
Relocation and installation of the pumping line that connects the open well to the concrete water tank to a safe location to avoid any future destruction due to rainwater flow in the valley.
Construction/supply/installation of house connections and provision of the remaining required materials to complete the construction of the water network with a total length of 18,000 meters.
Provision and installation of 820 water consumption meters.